Project Description
Install POE switches for the Lync rollout project.
Task Name | Duration | Install Date |
Phase II: Switch Deployment for FLC | 648 hrs | |
Create WBS | 4 hrs | Done |
Send and Receive Quotes | 9 days | Done |
PO Created and Sent to Alcatel | 7 days | Done |
Receive Build Switches | 2 days | Done |
Campus Services | 4 hrs | Done |
TC 1.1 | 3.33 hrs | Done |
Build Switches in Stock | 1 hr | Done |
Communicate Downtime to End Users | 10 mins | Done |
Install Switches | 1 hr | Done |
Configure Switches | 40 mins | Done |
Testing | 15 mins | Done |
Add Switch to E911 and Radius | 15 mins | Done |
Admin Building | 3 hrs | Done |
TC 1.1 | 3.5 hrs | Done |
Build Switches in Stock | 1 hr | Done |
Communicate Downtime to End Users | 5 mins | Done |
Install Switches | 1 hr | Done |
Install UPS | 30 mins | Done |
Configure Switches | 40 mins | Done |
Testing | 10 mins | Done |
Add Switch to E911 and Radius | 5 mins | Done |
FL1 B | 7 hrs | Done |
TC 1.3 (ALL Switches Have Arrived) | 3.75 hrs | Done |
Communicate Downtime to End Users | 10 mins | Done |
Install Switches | 10 mins | Done |
Configure Switches | 3 hrs | Done |
Testing | 10 mins | Done |
Add Switch to E911 and Radius | 15 mins | Done |
MDF (Ariving Dec 13 or 16) | 3 hrs | Done |
Communicate Downtime to End Users | 10 mins | Done |
Install Switches | 2 hrs | Done |
Configure Switches | 30 mins | Done |
Testing | 10 mins | Done |
Add Switch to E911 and Radius | 10 mins | Done |
Physical Education | 2 hrs | Done |
TC 1.1 (ALL Switches Have Arrived) | 2 hrs | Done |
Communicate Downtime to End Users | 10 mins | Done |
Install Switches 10am | 10 mins | Done |
Install Repourposed UPS From ? | 20 mins | Done |
Configure Switches | 1 hr | Done |
Testing | 10 mins | Done |
Add Switch to E911 and Radius | 10 mins | Done |
FL4 | 4 hrs | Done |
TC 1.2 (ALL Switches Have Arrived) | 4 hrs | Done |
Communicate Downtime to End Users | 10 mins | Done |
Install Switches | 1 hr | Done |
Configure Switches | 2.5 hrs | Done |
Testing | 10 mins | Done |
Add Switch to E911 and Radius | 10 mins | Done |
FL2 | 5 hrs | Done |
TC 1.2 (ALL Switches Have Arrived) | 2 hrs | Done |
Communicate Downtime to End Users | 10 mins | Done |
Install Switches | 45 mins | Done |
Configure Switches | 40 mins | Done |
Testing | 10 mins | Done |
Add Switch to E911 and Radius | 15 mins | Done |
TC 2.1 (ALL Switches Have Arrived) | 2 hrs | Done |
Communicate Downtime to End Users | 10 mins | Done |
Install Switches | 45 mins | Done |
Configure Switches | 40 mins | Done |
Testing | 10 mins | Done |
Add Switch to E911 and Radius | 15 mins | Done |
Project Timing
- Start Date: 01-06-2014
- Predicted End: 01-31-2014