Project Status For: SCC, POE Switch: SCC Install Phase II

Project Description

Install Switches

Project Timing

  • Start Date: 01-09-2012
  • Predicted End: 02-27-2015

Current Tasks

  1. Preliminary meetings for switch and phone counts completed

Current Holds

  1. Waiting for PO's to be created
 

Project Overview and Overall Progress

20% 20%

40% 40%

60% 60%

80% 80%

Project Discussion

Leave a Reply