Project Description
The following tentative dates have been set for FLC, however switch order delays have affected delivery time lines.
Admin | 25 | 11/7 | Open |
Campus Services | 8 | 11/7 | 11/15 10am |
FL1B | 15 | 11/18 (order) | 12/4 |
FL1, PE | 37 | 12/2 (order) | Target by 1/15 |
Fl4 | 12 | 12/4 (order) | Target by 1/15 |
Fl2 | 35 | 12/6 (order) | Target by 1/15 |
Project Timing
- Start Date: 11-01-2013
- Predicted End: 03-31-2014